Midtown Union Tower — Level 12 Interior Finishes

Brasfield & Gorrie · Atlanta, GA · Bid due July 10

Needs review
Materials
$4,720
Labor
$9,090
Overhead & margin
$2,486
Bid total
$16,296
AreaQtyLaborAI confidence
Level 12 Corridor Walls
Prime + 2 coats SW ProMar 200 Zero VOC, eg-shel, over Level 4 GWB
8,420 SF68 hrsHigh
Open Office Ceilings
1 coat SW Eminence flat, spray applied, exposed structure masked
12,150 SF52 hrsHigh
Hollow Metal Doors & Frames (24 EA)
SSPC-SP3 power-tool clean, spot prime, 2 coats DTM alkyd semi-gloss
24 EA46 hrsMedium
Break Room Accent Walls
2 coats accent color TBD by Architect — color schedule not yet issued
1,240 SF14 hrsReview
Stair 3 Rails & Stringers
Degrease SSPC-SP1, 2 coats waterbased alkyd semi-gloss — verify if epoxy intended
260 LF22 hrsReview
Spec evidence
Every AI line item links to the exact spec paragraph it came from. Click a row to verify it.
09 91 23Interior Painting§2.3.B · p.4
Verbatim from spec
Interior gypsum board, walls: one coat primer, two finish coats, eg-shel sheen. Basis of design: Sherwin-Williams ProMar 200 Zero VOC.
Scope of work: Prime + 2 coats SW ProMar 200 Zero VOC, eg-shel, over Level 4 GWB
Material: $1,890 · Labor: $3,060 · 2 coats