Back
Midtown Union Tower — Level 12 Interior Finishes
Brasfield & Gorrie · Atlanta, GA · Bid due July 10
Needs review
Materials
$4,720
Labor
$9,090
Overhead & margin
$2,486
Bid total
$16,296
| Area | Qty | Labor | AI confidence |
|---|---|---|---|
Level 12 Corridor Walls Prime + 2 coats SW ProMar 200 Zero VOC, eg-shel, over Level 4 GWB | 8,420 SF | 68 hrs | High |
Open Office Ceilings 1 coat SW Eminence flat, spray applied, exposed structure masked | 12,150 SF | 52 hrs | High |
Hollow Metal Doors & Frames (24 EA) SSPC-SP3 power-tool clean, spot prime, 2 coats DTM alkyd semi-gloss | 24 EA | 46 hrs | Medium |
Break Room Accent Walls 2 coats accent color TBD by Architect — color schedule not yet issued | 1,240 SF | 14 hrs | Review |
Stair 3 Rails & Stringers Degrease SSPC-SP1, 2 coats waterbased alkyd semi-gloss — verify if epoxy intended | 260 LF | 22 hrs | Review |
Spec evidence
Every AI line item links to the exact spec paragraph it came from. Click a row to verify it.
09 91 23Interior Painting§2.3.B · p.4
Verbatim from spec“Interior gypsum board, walls: one coat primer, two finish coats, eg-shel sheen. Basis of design: Sherwin-Williams ProMar 200 Zero VOC.”
Scope of work: Prime + 2 coats SW ProMar 200 Zero VOC, eg-shel, over Level 4 GWB
Material: $1,890 · Labor: $3,060 · 2 coats